CTE Enns will start construction works March 2019 15/02/19
< Zurück
With +40% Volume compared to year 2015 - CTE Enns will start construction works - on 4th of March 2019.
Duration: 03-08 2019 - 5 month's time to establish:
- +45.000sqm new terminal storage areas
- 1500meter new railtracks
- 2 new automated gates with ocr
- 1 brand new KUENZ RMG (the forth crane in Enns)